Latest traffic news
Works to divert services and install ducts are complete well ahead of schedule however a clash was identified requiring the design to be updated and the ordering of pile cages delayed by one week. Tree clearance and vegetation is complete in advance of the arrival of over wintering birds, necessary to avoid the project being delayed until after the winter.
Note, that we were able to persuade Northern PowerGrid to undertake their works when they did using a cancellation in their programme, otherwise we would have been waiting many months and commencing works in the depth of winter leading to the closure taking much longer.
Installation of the site compound continues this week. Excavation of the highway is commencing this week with silt fencing being installed on the river bank followed by removal of the surfacing material.
